Site Comparison Stage Missing from Pre-Construction Bird Strike Assessment Regulations for New Airports

On November 18, 2026, the Seoul High Court upheld a lower court ruling that canceled the basic plan for Saemangeum International Airport. The lower court found that the Ministry of Land, Infrastructure and Transport did not assess bird strike risk when comparing 13 candidate sites in 2019. The project site's estimated annual bird strikes ranged from 10.5 to 45.9 within a 13 km radius, higher than domestic airports compared by the lower court (0.007 to 3.0). The Airport Facilities Act does not list bird strike risk among the required items for basic plans, and the Ministry's notification only requires assessment "in advance of airport construction." The Ministry of Climate, Energy and Environment's bird assessment guidelines apply to applications received from 2026 onward, and basic plans for Gadeokdo, Jeju Second, and Daegu-Gyeongbuk new airports were notified before that date.